PV2 Investment JSC announces
the proceed usage report as follows:
On December 2010, PV2
Investment JSC rise successfully the capital charter from VND 182,507,080,000
to VND 373,500,000,000. The proceed usage was:
No.
|
Project
|
Distributed investment capital as planned (VND)
|
Exercise Investment capital (VND)
|
1
|
The Executive
Villas Project at Nhon Trach, Dong Nai
|
50,460,000,000
|
50,460,000,000
|
2
|
The Office
Building Project at Bien Hoa, Dong Nai
|
2,821,000,000
|
2,821,000,000
|
3
|
The housing
project for employee of the Oil Refinery Dung Quat
Dự án Nhà ở
CBCNV Nhà máy Lọc dầu Dung Quất
|
77,712,000,000
|
2,000,000,000
|
4
|
Supplement
business capital and disburse followed by the process of teh project
|
60,000,000,000
|
135,712,000,000
|
|
Total
|
190,993,000,000
|
190,993,000,000
|
The
reason for not using up all the raised capital from the placement: the housing
project for employee of the oil refinery Dung Quat is rescheduling the process.
HNX
|