- Name of project: B1, B2, B3
- Investor: Thien Long Group Corporation
- Design Consulting Organization: Phuong Nam Construction Consultant & Computer – Investment Joint Stock Company
- Purpose of investment: to build office, factory, warehouse & all kinds of stationery (ball- point pen, pen, pen brush & crayon)
- Investment scale:
+ Total land area: 15,750.00 m2
+ Total construction area: 9,043.53 m2
+ New construction area: 2,135.52 m2
+ Total floor area: 8,542.08 m2
+ Number of stories: 4 floors
- Construction location: lot 6-8-10-12 Street 3, Tan Tao Industrial Park, Binh Tan District, Hochiminh.
- Expected investment value in 2017: VND128,500,000,000 (including construction investment VND74,100,000,000 & devices VND54,000,000,000)
- Expected investment resources: 50% equity & 50% borrowed funds
- Time of implementation:
+ Preparation phase: from November 21, 2016 to March 18, 2017
+ Carrying out by construction: from March 20, 2017 to November 02, 2017
+ Devices installation: from November 03, 2017 to November 14, 2017
+ Official operation: November 15, 2017. HOSE
|