Saturday, 26/07/2008 16:16

Gas turbine No 2 at Nhon Trach Gas-fuelled Power Plant kick-started

The second gas turbine at the Nhon Trach Gas-fuelled Power Plant was successfully kick-started in the afternoon of July 23.

The turbine is in the run-in period and other equipment is being adjusted for an official linkage to the national grid on July 26.

The first gas turbine of the plant was officially handed over by EPC contractor Lilama to its investor, the Vietnam Oil and Gas Electricity Corporation on June 30 and is generating electricity to the national grid.

Workers are also urged to boost efforts so that the steam turbine will be completed by February 2009 and the whole combined cycle of the plant will become officially operational by March 2009.

ND

Other News

>   Seminar discusses ways to promote corporate governance (26/07/2008)

>   Some taxi companies in Hanoi increase fares (26/07/2008)

>   Nearly $45bil FDI registered into VN (26/07/2008)

>   HSBC introduces Vietnam to Japanese businesses (26/07/2008)

>   Country maintains stable economic growth in July (26/07/2008)

>   Indochina Capital CEO pleased with Vietnam’s business environment (26/07/2008)

>   Vietnam attracts over US$45.2 billion in FDI in seven months (25/07/2008)

>   Subsidising petroleum prices: the flip side of the coin (25/07/2008)

>   Investors still turning backs on projects for lower class (25/07/2008)

>   Coping with inflation: cutting jobs, narrowing business scale (25/07/2008)

Online Services
iDragon
Place Order

Là giải pháp giao dịch chứng khoán với nhiều tính năng ưu việt và tinh xảo trên nền công nghệ kỹ thuật cao; giao diện thân thiện, dễ sử dụng trên các thiết bị có kết nối Internet...
User manual
Updated version