Pacific Infrastructure Project Development and Investment Corporation sent documents to HOSE to request to delay the disclosure of its financial statements in 2017 as follows:
- For the quarterly financial statements:
- Quarter 01, 2017 : from April 20, 2017 to April 30, 2017
- Quarter 02, 2017: from July 20, 2017 to July 30, 2017
- Quarter 03, 2017: from October 20, 2017 to October 30, 2017
- Quarter 04, 2017: from January 20, 2018 to January 30, 2018
- For the reviewed semi-annual financial statements: from August 14, 2017 to August 31, 2017
- For the audited annual financial statements: from March 31, 2018 to April 10, 2018.
However, the request of PPIwill be reviewed and approved in writing by the State Securities Commission.
|