NT2: Nhon Trach 2 Power Plant Overhauled
NT2 Joint Stock Company (NT2) announces that it finished the complete overhaul of Nhon Trach 2 Power Plan on October 03, 2017 after 32 days of repair, 6 days ahead of schedule. After the overhaul, the total output power of machine units increased by 24MW.