PXT: PVC-PT signs a construction contract On May 19, 2016, the Board of Directors of Petroleum Pipeline & Tank Construction Joint Stock Company (PVC-PT) authorized the CEO to negotiate and sign a contract with the parent company Petrovietnam Construction Joint Stock Corporation (PVC) for Package No.4: Building the steel structure of coal storage for the Song Hau 1 Thermal Power Plant Project.
- Total estimated value of contract: VND115,592,991,186 (VAT excluded)
- Contractual party: Petrovietnam Construction Joint Stock Corporation (PVC)
- Contractor: LILAMA Corporation
- Investor: Vietnam Oil and Gas Group
- Estimated construction time: 597 days, from July 01, 2016 to March 13, 2018. HOSE
|