Ha Noi cancels land-use certificates for 19 projects
The Ha Noi People's Committee has cancelled land-use rights for 13 projects on a total of 14 ha that did not start on schedule despite extensions.
Committee Deputy Chairman Vu Hong Khanh had asked that the city's administrators to determinedly cancel projects that did not the conditions of their land-use certificates as well as work with investors to quicken the construction of on-going projects.
Ha Noi Natural Resources and Environment Department officials have inspected another 32 projects delayed within 12 months of receiving land-use certificates.
The projects on more than 76 ha were given a six-month extension in February.
The inspectors found that work had started on 21 of the projects and some had been completed.
But the people's committee instructed district administrators to cancel six on almost 13ha of land because of the lack of progress.
Another five are awaiting planning adjustment or land clearance process.
The Ha Noi Planning and Investment Department and Land Clearance Steering Board says that more than 50 projects are slow moving.