S99: Results of Annual General Meeting of Shareholders 2009
Song Da No 9.09 JSC has disclosed the results of its Annual General Meeting of Shareholders held on 17/04/2009. The following resolutions were approved:
1. Operating results of 2008:
Unit: VND
1.1. Production: |
103.649 billion (105.98% of plan) |
- Construction |
103.649 billion |
- Investment |
7.245 billion |
1.2. Revenue |
90.806 billion (106% of plan) |
1.3. Work in progress as of 31/12/2008: |
28.424 billion. |
1.4. Profit before tax |
19.601 billion. |
1.5 Cash transferred to the Company’s account |
111 billion (143% of plan) |
1.6. Total actual cost |
71.646 billion |
1.7. Book value of fixed asset at closing balance |
58.187 billion |
1.8. Payables to the State |
5.815 billion ( 72% of plan) |
1.9. Average income |
4,067,861/ person/month |
1.10. Receivables as of 31/12/2008: |
28.814 billion |
1.11. Payables as of 31/12/2008:
+ Banks:
+ Customers:
|
44.090 billion
32.111 billion
11.978 billion |
2. Plan for 2009:
2.1. Production: |
124.095 billion |
- Construction |
123.095 billion |
- Trade and services |
1.000 billion |
2.2. Projects |
7.061 billion |
2.2. Revenue |
138.178 billion |
2.3. Profit before tax |
22.212 billion |
2.4. Cash transferred to the Company’s account |
115 billion |
2.5. Payables to the State |
6.321 billion |
2.6. Average income |
4,165,916 / person/month |
2.7. Total actual cost |
104.312 billion |
2.8. Book value of fixed asset at closing balance |
51.812 billion |
2.9. Operating Capital |
121.186 billion |
2.10. Receivables |
19 billion |
2.11. Payables |
45 billion |
3. Investment 2008
- Tan Van lot project in Tan Van, Bien Hoa City, Dong Nai Province: looking for partner to transfer the project.
- Phinh Ho Hydropower plant Project: Tram Tau, Yen Bai province - goals for 2008 not achieved. Completed items: compensation for ground clearance, cart ways.
- Ngoc Khanh Project:
Completed items: sociological survey, drawing for the project, agreement on total area
- Vinh Ho Project: under planning
- Others: Investment in heavy vehicles and equipment for construction
4. Investment plan for 2009
- Tan Van project: Transfer the project .
- Phinh Ho Hydropower plant Project, Ngoc Khanh Project and Vinh Ho Project: to be continued.
5. Reports from the Board of Directors, plan for 2009.
6. Audited financial statement 2008.
No. |
Indicators |
Unit |
Amount |
1 |
Owner’s equity, including: |
VND |
52,457,814,766 |
|
Business capital |
VND |
29,739,700,000 |
|
Share premium |
VND |
606,000,000 |
|
Treasury stock |
VND |
(260,300,000) |
|
Funds and retained earnings |
VND |
17,277,746,695 |
2 |
Revenue |
VND |
85,095,110,277 |
3 |
Profit before tax |
VND |
19,601,621,919 |
4 |
Profit after tax |
VND |
16,857,394,851 |
7. Plan of seasoned issue to increase charter capital from VND 29.7397 billion to VND 80 billion.
8. Profit distribution 2008
Profit after tax |
16 ,857 ,394 ,851 |
Reduced income tax
(Transferred to the Investment and Develop
Unit: VND
ment Fund) |
2 ,744 ,227 ,068 |
PROFIT FOR DISTRIBUTION |
14 ,113 ,167 ,783 |
- Reward and welfare fund (8% profit after tax) |
1 ,129 ,053 ,423 |
- Financial reserve fund (3%profit after tax) |
423 ,395 ,033 |
- Dividend payment by share, exercise rate 40% |
11 ,791 ,760 ,000 | Unit: VND
- Bonus shares issued to outstanding shareholders |
768 ,959 ,327 |
RETAINED EARNINGS |
0 |
9. Assign the BOD to select auditor for 2009.
10. Remuneration for the BOD, Supervisory Board and the Company’s Secretary.
11. Assign the BOD to approve the project on the Residential Apartment Buildings A2,B1,B2,B3 at Ngoc Khanh, Ba Dinh, Hanoi.
12. Mr. Le Van Hung has been appointed Director in place of Mr. Nguyen Dang Lanh
HNX
|