According to the Board resolution dated February 24, 2021, the Board of Directors of Gia Lai Electricity Joint Stock Company approved the investment plan for Tan Phu Dong 2 Wind Power Plant Project, as follows:
- Project: Tan Phu Dong 2 Wind Power Plant
- Investor: Tien Giang Wind Power Joint Stock Company (TGE)
- Capacity: 50MW
- Location: Tan Thanh, Go Cong Dong, Tien Giang province.