DRC: Board Resolution No.04 Danang Rubber Joint Stock Company announced Resolution No.12 of the Board of Directors on July 16, 2012:
Article 1: The Board of Directors approved to adjust the package
price for supplement of fork-lift trucks belonging to project “Radial Tire
Factory with a capacity of 600,000 tires/year”:
-
Adjusted price of the
package: US$587,659, or VND12,240,000,000.
The work included VAT and other taxes and fees.
Exchange rate: 1 US$ = 20,828 VND
Article 2: The Board of Directors approved design and cost estimate
of project “Moving the Motor Tire and Tube Enterprise
from North of My An to Lien Chieu Industrial Zone”.
-
Cost estimated:
VND579,098,064,000 (including VAT)
Including:
Building cost:
|
VND
|
253,941,486,000
|
Equipment cost:
|
VND
|
217,731,619,000
|
+ New equipment
|
VND
|
50,449,169,000
|
+ Cost of dismantling, transporting and
installing equipment
|
VND
|
167,282,450,000
|
Project management cost
|
VND
|
6,441,182,000
|
Consulting fee
|
VND
|
14,855,552,000
|
Other costs
|
VND
|
51,426,199,000
|
Reserve cost
|
VND
|
34,702,026,000
|