EVN to borrow over US$3 billion for power projects

The Electricity of Vietnam (EVN) will borrow more than US$2 billion from ODA sources and US$1 billion in commercial loans for its major power projects in 2012.

The group plans to sign with the World Bank a US$378.9 million loan, a US$330 million loan for improving the efficiency of the distribution network and a US$200 million loan for the reform of the power sector.

It will also conduct negotiations with the German Reconstruction Bank (KfW) on a US$330 million credit for the O Mon Power Plant No. 4.

EVN will also seek capital from the KfW for a 300 million EUR power transmission network investment programme, a 200 million EUR Smartgrid development plan and the US$120 million second phase of a project to increase energy efficiency in rural areas.

EVN said it will urge the Asian Development Bank to arrange for US$1 billion loan from the WB, KfW, the French Development Agency (AFD) and the Japan International Cooperation Agency (JICA) so that it can upgrade and expand the power distribution network.

The new capital sources are expected to allow the group to put into operation eight turbines in four hydropower projects with a combined capacity of 1,373MW and start the construction of four thermo-electric power plants with a combined capacity of 2,390 MW.

The group will also prepare for the infrastructure of Ninh Thuan nuclear power centre.

vov

Other News

>   Industries urged to take inflation-control measures (09/01/2012)

>   Vietnam tries to tighten the lending to fund outward investment (09/01/2012)

>   Poor land management wastes public funds (07/01/2012)

>   PM Dung says State construction projects require better planning (07/01/2012)

>   Dong Nai approves hi-tech projects for industrial park (07/01/2012)

>   Corporate income tax rules set to change (07/01/2012)

>   Vietnam strives for trade balance by 2020 (07/01/2012)

>   Construction sector urged to continue good work (07/01/2012)

>   Seminar highlights ADB’s assistance to VN (07/01/2012)

>   Deputy PM asks for petrol checks in wake of auto fires (06/01/2012)

Online Services
iDragon
Place Order

Là giải pháp giao dịch chứng khoán với nhiều tính năng ưu việt và tinh xảo trên nền công nghệ kỹ thuật cao; giao diện thân thiện, dễ sử dụng trên các thiết bị có kết nối Internet...
User manual
Updated version