Tuesday, 06/04/2010 17:31

Dung Quat oil refinery to finish in April

The Vietnam Oil and Gas Group (PVN) and the contractor of the Dung Quat oil refinery, Technip are stepping up the negotiation process to put the oil refinery into operation in April, said a PVN representative at a press conference in Hanoi on April 5. 

Technip has fixed all the technical errors in half of its 4 contracts. The remaining contracts however still have some minor problems, but they do not affect the oil refinery operating stably.

PVN said the Prime Minister has agreed to allow PVN to conduct further negotiations with Technip and control the remaining contracts in case Technip shows the highest sense of responsibility when ensuring the quality of the contracts.

PVN Chairman Dinh La Thang, said that there will be some hiccups during the initial trail run and the plant will only operate smoothly after one or two years.

vov

Other News

>   Nissan sells locally-assembled cars in Vietnam (06/04/2010)

>   Garment exports top estimates in first quarter (06/04/2010)

>   PetroVietnam achieves 76% growth in revenue (06/04/2010)

>   IT industry's future far from certain (06/04/2010)

>   Property firms build up hopes (06/04/2010)

>   Thu Thiem Tunnel section towed to site (06/04/2010)

>   Government dedicated to freeze on construction costs (06/04/2010)

>   State President urges Vinh Long to develop infrastructure (06/04/2010)

>   Power shortage and countermeasures (06/04/2010)

>   Wasting dollar on luxuries expands trade deficit (06/04/2010)

Online Services
iDragon
Place Order

Là giải pháp giao dịch chứng khoán với nhiều tính năng ưu việt và tinh xảo trên nền công nghệ kỹ thuật cao; giao diện thân thiện, dễ sử dụng trên các thiết bị có kết nối Internet...
User manual
Updated version