Wednesday, 13/05/2009 19:32

First turbine of Quang Ninh 1 power plant joins the national grid

The first turbine of Quang Ninh 1 thermo-electric power plant with a capacity of 300 MW officially joined the national grid at 10:30 am on May 12.

In the first phrase, Quang Ninh 1 thermo-electric power plant has 2 turbines with a capacity of 600 MW. Also, the second phrase with 2 more turbines generating 600 MW will raise the total capacity of the plant to 1,200 MW. As a result, the plant will generate 3.6 billion kWh annually to the national grid.

This project is an engineering, procurement and construction (EPC) contract between the Quang Ninh Thermal Power Joint Stock Company and the Shanghai Electric Group Co., Ltd (SEC) with a total investment capital of more than US$452 million. The Vietnam Electricity Group (EVN) invests in the construction of this project with an investment of VND 9,165.2 billion.

nhandan

Other News

>   Microsoft provides 3 solutions for SMEs to control cost (13/05/2009)

>   US likely to become largest foreign investor in Vietnam within the next 2 years (13/05/2009)

>   Five pct GDP growth rate out of reach? (13/05/2009)

>   Infrastructure fund to be created (13/05/2009)

>   Retail remains most attractive industry in Vietnam (13/05/2009)

>   Not easy to hunt for cheap houses in US (13/05/2009)

>   CIEM gives three scenarios for Vietnam’s economy in 2009 (13/05/2009)

>   Goods pile up at backlogged port (13/05/2009)

>   Singapore firm pulls out of chemical project (13/05/2009)

>   Businessmen complain about regulation on quoting prices in VND (13/05/2009)

Online Services
iDragon
Place Order

Là giải pháp giao dịch chứng khoán với nhiều tính năng ưu việt và tinh xảo trên nền công nghệ kỹ thuật cao; giao diện thân thiện, dễ sử dụng trên các thiết bị có kết nối Internet...
User manual
Updated version